Reitanlage Haidt – outdoor riding area
Renewal of footings at Gut Haidt
Optimum training conditions thanks to new, perfectly matched, allround footings, including installation service.
Properties
- Year of implementation: 2014
- Nature of surface: Mossy, a lot of mud
- Area: 1200 m²
- Construction time: 1 day
- Customer: Reiterhof Gut Haidt, Christian Schuster-Stengel, 95028 Hof
Project description
The existing riding area was on one hand very deep and uneven, and at the same time there was increased danger of slipping due to a lack of grip in the footings. In only one day, the complete restoration of the footings on the riding facility of Mr Schuster-Stengel was carried out. This included laying the new, matched Allround footings and the mixing of the aggregates. Thanks to the new, functional surface, the riding area is now weatherproof and ridable throughout the year. The high-quality aggregates add optimum grip, elasticity and slip resistance, even during bad weather. At the same time, we were able to reduce dust formation noticeably with a higher level of moisture in the surface.